City Council has set a very aggressive timeline that Ellis Don feels is achievable. The following outlines timelines for the various amenities on the site. Watch this area for more updates and current pictures of the progress of the project.
| Council Approval |
June 30 2009 |
| Demolition Permit |
June 30 2009 |
| Site Plan Approval Application |
July 22 2009 |
| Fdn/Structure Permit Apply |
July 29 2009 |
| Site Plan Approval by |
Aug 18 2009 |
| Site Grading Commences |
Aug 19 2009 |
| Fdn/Structure Permit by |
Sept 08 2009 |
| Building Commences |
Sept 09 2009 |
| Substantial Completion –Ice! |
Sept 01 2010 |